The construction of clay firebrick will be completed in different seasons, but due to different environmental requirements, the construction operation of brick requirements will also have corresponding changes, and it is necessary to pay attention to the precautions of construction in different seasons.
1. It can be constructed in early winter, and it is not recommended to lay clay firebricks in the cold stage.
2. The use temperature of mortar shall not be less than 5 degrees, and anti-freezing measures shall be taken before the mortar is hardened.
3. It is not suitable to construct clay firebrick on the outer wall in rainy days. If construction is required, a canopy should be erected.
4. In summer, take effective measures to prevent exposure to the sun and prevent the loss of water in the adhesive layer from producing a hollow drum too quickly.
To sum up, due to the different requirements of each environment, when laying clay firebrick, it is necessary to pay attention to various situations that are not conducive to the construction of firebrick, in order to avoid and better ensure the construction quality.